Commercial electrical · 6 min read
Check a commercial space’s electrical capacity before signing the lease
A prelease electrical review connects equipment needs, tenant feeders, building capacity and landlord responsibilities before the opening date is committed.
YKCA Journal · Sources reviewed October 3, 2026
Explore the guide
Commercial electrical: browse all five guides ↗
The key decision
A panel rating and a few empty breaker spaces do not establish that a commercial suite can support your business. Match a written equipment schedule to the complete supply path before committing to the space.
The decision before the deposit
Before signing, determine whether the space can support the equipment you intend to operate and what must happen if it cannot. A workable result is a documented assessment with identified assumptions, upgrade options and responsible parties. A verbal statement that the unit has commercial power is too vague to support an opening schedule. Even a photograph of a panel label says little about the available capacity of shared building equipment upstream.
The practical question is not simply whether an electrician can add outlets. It is whether the proposed business can receive compatible power at the required locations, with a construction path the landlord permits. Treat the assessment as due diligence tied to your equipment and operating plan. It can reveal a modest branch-circuit project, an unresolved utility project or a space that deserves a different business layout.
Build an equipment schedule that reflects opening day
Write down the equipment you expect to install, including major appliances, HVAC changes, lighting, printers, rack equipment, signage and any charging. For each selected product, obtain its actual electrical documentation. Include voltage, phase, rated input, connection type and operating pattern. Mark undecided products as assumptions rather than borrowing specifications from a similar model. A restaurant and an office with the same floor area can have very different electrical needs.
Identify what operates together. A startup may plan to add equipment later, but the first busy day can already combine cooling, cooking, hot water and refrigeration. Tell the design team which future additions are likely and which are speculative. Prioritizing the first phase prevents a vague growth wish from becoming an unnecessarily large construction requirement, while still protecting a feasible expansion route.
Follow the power beyond the suite panel
The electrician needs to identify the actual service arrangement, tenant feeder, panel ratings, existing loads and shared distribution serving the space. A new subpanel can provide more circuit positions without increasing what the feeder or service can deliver. Two panel ratings cannot simply be added together to prove that they are equivalent to a promised supply. Voltage and phase compatibility remain separate questions.
Ask for a plain-language description of the limiting component and what evidence supports that conclusion. Existing drawings and operating records can help, but they must match the current building. If the review depends on utility confirmation or engineering work not yet completed, record that dependency. OSHA addresses equipment ratings, installation and access; its requirements reinforce the importance of reviewing equipment suitability rather than treating a panel enclosure as an unrestricted source.
Turn the landlord work letter into a construction boundary
The lease should identify who controls meter rooms, risers, shared switchgear and access routes. Your business may be responsible for equipment inside the suite while the landlord controls the upstream system. That division affects approvals, contractor selection and the ability to shut down neighboring tenants. Have your real estate and legal advisers clarify the contractual responsibilities; an electrical assessment establishes the technical facts they need.
Ask whether common-area pathways, exterior equipment, roof access or a new meter location are allowed. An otherwise reasonable electrical design may conflict with property rules or require another approval. Record who authorizes an outage, how notice is issued and which operating hours are available. These details belong in the project assumptions, because an inexpensive installation that cannot be scheduled is not a useful opening plan.
Illustrative scenario: two panels and one promise
Consider an illustrative retailer planning a small production area behind the storefront. The listing describes a 200A supply, while the proposed landlord work consists of two 100A panels. The tenant’s selected equipment includes a three-phase machine. The right next step is to have the actual supply arrangement and machine requirements reviewed together. Neither the panel count nor the total of their labels answers whether the selected machine can operate.
Suppose the review finds that ordinary retail circuits can be added, but the machine requires a different building connection and landlord approval. The tenant can compare an alternative machine, a revised production plan or a utility-supported upgrade before signing a construction contract. This is a planning example, not a YKCA project or a prediction about a particular property. Its value is showing which decision should precede equipment delivery.
Compare proposals on the same assumptions
Request a proposal that separates existing-condition verification, design, suite wiring and any base-building or utility work. Include equipment selections, circuit destinations, pathway assumptions, permit responsibilities, patching and outage windows. If the contractor has not verified hidden conditions, the proposal should identify the allowance or follow-up investigation. A budget based on incomplete drawings should not be treated as a fixed construction scope.
PG&E’s commercial project resources describe a separate design, contract, construction and meter-connection process for service projects. That is a useful reminder to distinguish work inside the suite from a change requiring utility involvement. It does not establish that your particular space needs an upgrade or how long your project will take. Ask which milestones are confirmed and which depend on another party before using the proposal to set an opening date.
Mistakes that make the lease harder to unwind
Do not choose a space because the panel has spare positions, assume neighboring tenants’ equipment proves your capacity, or order an appliance before confirming its supply. Another common mistake is requesting a quote for a number of outlets without identifying the equipment they will serve. Receptacle quantity describes convenience and layout; it does not establish load or compatibility.
Avoid treating the former tenant’s operations as an approved basis for yours. Their load, permit history and equipment may differ. Preserve photographs of accessible labels and existing documents, but leave panel opening and electrical measurements to qualified personnel. If your due diligence leaves a critical uncertainty, make that visible to the advisers negotiating the lease instead of burying it in an informal contractor conversation.
A useful outcome for the next meeting
You should leave the review with an equipment schedule, a description of the actual supply, identified constraints and a clear division of responsibilities. The business owner can then decide whether the remaining uncertainty is acceptable or whether to pursue another space. The landlord can review the requested changes, and the electrical team can develop a scope with fewer unresolved selections.
For a planned buildout, discuss these records through YKCA’s tenant improvement electrical service. Bring the suite address, intended use, current plans, selected equipment and landlord work letter. Ask for the scope needed to move from preliminary assessment to construction, rather than a generic cost per square foot. A decision supported by these records is easier to coordinate with the rest of the buildout and easier to revise when the business plan changes.
Put it into practice
A decision table to keep handy
| Observation | What it establishes | What still needs review |
|---|---|---|
| Empty breaker positions | Possible circuit layout space | Feeder, service and proposed load |
| Panel marked 200A | Equipment rating | Actual supply and remaining capacity |
| Three-phase equipment selected | A compatibility requirement | Available voltage and phase |
| Landlord promises an upgrade | A proposed contractual task | Approved design, owner and schedule |
Bring this to the conversation
Your next-step checklist
Common questions
Does a larger panel guarantee more power?
No. The feeder and upstream supply must support it. The panel’s rating is only one part of the assessment.
Can we assess a space before the final equipment list is complete?
Yes, but identify assumed equipment and the decisions that could change the result. Use a preliminary assessment as a planning document.
Who decides whether the lease protects us?
Your real estate and legal advisers assess the agreement. The electrical team provides the verified technical conditions and proposed construction boundaries.
The questions behind this guide
Problems people are trying to solve.
These public discussions illustrate reader concerns. They are not technical instructions, local survey results or evidence of work performed by YKCA.
- Question about what my commercial landlord just told me?
Tenant was promised a 200A three-phase panel but landlord proposed two 100A panels; illustrates why amperage and phase promises need technical verification.
Check the original guidance
Sources & review date
Primary guidance and available source excerpts reviewed October 3, 2026. Requirements and program terms can change; verify the current instructions for your property and project before committing to work.